EV charging stations with canopies or batteries get fast-track permit approval
Cities and counties must give administrative approval to EV charging stations with canopies or onsite battery storage, not only basic chargers. They must send written notice within 30 days once an application is deemed approved, and update their fast-track permit rules.
Who it affects
EV charging station builders and city and county permit offices
When
This law takes effect on January 1, 2027. California laws take effect on January 1 of the year after they are signed, unless the law says otherwise.
- : Signed into law
- : This law takes effect
- : Cities and counties must update their EV permit ordinances